Level II scour analysis for brigde 5 (STOCTH00360005) on Town Highway 36, crossing Stony Brook, Stockridge, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure STOCTH00360005 on Town Highway 36 crossing Stony Brook, Stockbridge, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 23.0-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest on the left and right banks downstream and left bank upstream, while the right bank upstream is pasture with some shrubs and brush. In the study area, Stony Brook has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 109 ft and an average bank height of 11 ft. The channel bed material is predominantly gravel with a median grain size (D50) of 71.7 mm (0.235 ft). The geomorphic assessment at the time of the Level I site visit on April 12, 1995, and Level II site visit on July 9, 1996, indicated that the reach was stable. The Town Highway 36 crossing of Stony Brook is a 50-ft-long, one-lane bridge consisting of one 48-foot steel-beam span (Vermont Agency of Transportation, written communication, March 23, 1995). The opening length of the structure parallel to the bridge face is 46.3 ft. The bridge is supported by a vertical, concrete abutment on the left and a vertical, concrete abutment with wingwalls on the right. The channel is skewed approximately 5 degrees to the opening while the opening-skew-to-roadway is 0 degrees. A scour hole 2.0 ft deeper than the mean thalweg depth was observed during the Level I assessment along the left side of the channel at the downstream bridge face where the flow impacts a bedrock outcrop. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the right bank upstream and at the upstream and downstream ends of the left abutment, type-2 stone fill (less than 36 inches diameter) at the upstream end of the upstream right wingwall, and type-3 stone fill (less than 48 inches diameter) at the downstream end of the downstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 2.0 to 3.2 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 9.7 to 22.2 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont

Level II scour analysis for Bridge 43 (CHESVT00110043) on State Highway 11, crossing the Middle Branch Williams River, Chester, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure CHESVT00110043 on State Route 11 crossing the Middle Branch of the Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is principally in the Green Mountain section of the New England physiographic province in southeastern Vermont. The 13.7-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly forest except for the area downstream and right of the bridge which is pasture. In the study area, the Middle Branch of the Williams River has a sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 77 ft and an average bank height of 8 ft. The channel bed material ranges from gravel to boulder with a median grain size (D 50 ) of 76.6 mm (0.251 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 11, 1996, indicated that the reach was laterally unstable. Lateral instability was evident from the several point bars and cut banks located through the study reach. The State Route 11 crossing of the Middle Branch of the Williams River is a 76-ft-long, two-lane bridge consisting of two 37-foot concrete Tee-beam spans (Vermont Agency of Transportation, written communication, March 29, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 35 degrees to the opening. The computed opening-skew-to-roadway was 30 degrees but the historical records indicate this angle is 25 degrees. Scour protection measures at the site consist of type-1 stone fill (less than 12 inches diameter) along the downstream banks and the upstream right wing wall. Type-2 (less than 36 inches diameter) stone fill protection is noted on the upstream and downstream left wingwalls and upstream along the left bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.5 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 7.2 to 10.7 ft. The worst-case abutment scour occurred at the 500-year discharge for the right abutment. Pier scour ranged from 7.3 to 8.6 ft. The worst-case pier scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont

Level II scour analysis for Bridge 38 (ANDOVT00110038) on State Route 11, crossing the Middle Branch Williams River, Andover, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure ANDOVT00110038 on State Route 11 crossing the Middle Branch Williams River, Andover, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in south central Vermont. The 5.65-mi 2 drainage area is in a predominantly rural and forested basin. Upstream and downstream of the study site banks and overbanks are forested. In the study area, the Middle Branch Williams River has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 44 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to boulders with a median grain size (D 50 ) of 54.0 mm (0.177 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 5, 1996, indicated that the reach was stable. The State Route 11 crossing of the Middle Branch Williams River is a 33-ft-long, two-lane bridge consisting of one 31-foot concrete T-beam span (Vermont Agency of Transportation, written communication, March 29, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 55 degrees to the opening while the measured opening-skew-to-roadway is 45 degrees. There were no scour problems observed during the Level I assessment. Type-4 stone fill (less than 60 inches diameter) and type-3 stone fill (less than 48 inches diameter) was present on the left bank upstream and right bank upstream respectively. Type-2 stone fill (less than 36 inches diameter) was present in the upstream left wing wall area. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.8 to 3.4 ft. The worst-case contraction scour occurred at the 500-year flow. Abutment scour ranged from 12.0 to 14.0 ft. The worst-case abutment scour occurred at the 500-year flow at the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont

Level II scour analysis for Bridge 26 (WSTOTH00070026) on Town Highway 7, crossing Greendale Brook, Weston, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure WSTOTH00070026 on Town Highway 7 crossing Greendale Brook, Weston, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in south central Vermont. The 3.13-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest. In the study area, the Greendale Brook has a sinuous, non-incised, non-alluvial channel with a slope of approximately 0.015 ft/ft, an average channel top width of 38 ft and an average bank height of 3 ft. The channel bed material ranges from sand to boulder with a median grain size (D 50 ) of 64.8 mm (0.213 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 19, 1996, indicated that the reach was laterally unstable. The channel has moved to the right, however, scour countermeasures are in place along the upstream right bank. The Town Highway 7 crossing of the Greendale Brook is a 52-ft-long, two-lane bridge consisting of one 50-foot steel-beam span with a concrete deck (Vermont Agency of Transportation, written communication, April 07, 1995). The opening length of the structure parallel to the bridge face is 48.6 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 50 degrees to the opening while the opening-skew-to-roadway is 30 degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the upstream right wingwall and right abutment during the Level I assessment. Scour protection measures at the site include: type-2 stone fill (less than 36 inches diameter) at the upstream end of the upstream left wingwall, along the left bank upstream, at the downstream end of the downstream left wing wall, and along the entire length of the downstream right wing wall; type 4 (less than 60 inches) and type-3 stone fill (less than 48 inches) along the right bank upstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was 0.0 ft. Abutment scour ranged from 3.9 to 9.9 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). The Hire equation (abutment scour) is often used when the horizontal length blocked by flow divided by the depth of flow is greater than 25 (Richardson and others, 1995 p. 49). Although the Hire equation could be applied to the left abutment more conservative scour estimates were given by the Froehlich equation on the left abutment. Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont

Level II scour analysis for Bridge 21 (MORETH00010021) on Town Highway 1, crossing Cox Brook, Moretown, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure MORETH00010021 on Town Highway 1 crossing Cox Brook, Moretown, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in north-central Vermont. The 2.85-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly forested. In the study area, Cox Brook has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 23 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to cobble with a median grain size (D 50 ) of 47.5 mm (0.156 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 18, 1996, indicated that the reach was stable. The Town Highway 1 crossing of Cox Brook is a 29-ft-long, two-lane bridge consisting of one 27-foot steel-beam span (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 24.8 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 60 degrees to the opening while the measured opening-skew-to-roadway is 40 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the left abutment downstream during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the left bank upstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100-year and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.2 to 0.5 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Abutment scour ranged from 2.8 to 4.0 ft. The worst-case abutment scour occurred at the left abutment at the 100-year discharge and at the right abutment at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont

Level II scour analysis for Bridge 4 (MAIDTH00070004) on Town Highway 7, crossing Cutler Mill Brook, Maidstone, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure MAIDTH00070004 on Town Highway 7 crossing the Cutler Mill Brook, Maidstone, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the White Mountain section of the New England physiographic province in northeastern Vermont. The 18.1-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly shrub and brushland. In the study area, the Cutler Mill Brook has a non-incised, meandering channel with local braiding and a slope of approximately 0.004 ft/ft, an average channel top width of 43 ft and an average bank height of 2 ft. The channel bed material ranges from sand to cobble with a median grain size (D 50 ) of 27.6 mm (0.091 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 19, 1995, indicated that the reach was laterally unstable due to large meanders in the channel. The Town Highway 7 crossing of the Cutler Mill Brook is a 25-ft-long, one-lane bridge consisting of one 22-foot concrete span (Vermont Agency of Transportation, written communication, August 5, 1994). The opening length of the structure parallel to the bridge face is 21.7 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 20 degrees to the opening while the opening-skew-to-roadway is 0 degrees. A scour hole 2.0 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along both banks upstream, along the entire base length of the upstream left wingwall, and along the upstream end of the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 2.2 to 4.2 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 5.7 to 12.4 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont

Level II scour analysis for Bridge 22 (WALDTH00180022) on Town Highway 18, crossing Coles Brook, Walden, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure WALDTH00180022 on Town Highway 18 crossing Coles Brook also known as Joes Brook, Walden, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in northeastern Vermont. The 12.5-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly forested while the downstream left bank is shrub and brushland. In the study area, the Coles Brook has an incised, sinuous channel with a slope of approximately 0.004 ft/ft, an average channel top width of 54 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to bedrock with a median grain size (D50) of 124.1 mm (0.407 ft). The D 50 was taken from a pebble count in the downstream channel, because the upstream channel is primarily bedrock. The geomorphic assessment at the time of the Level I and Level II site visit on August 8, 1995, indicated that the reach was stable. The Town Highway 18 crossing of the Coles Brook is a 46-ft-long, one-lane bridge consisting of one 44-foot steel-beam span with a wooden deck (Vermont Agency of Transportation, written communication, April 5, 1995). The opening length of the structure parallel to the bridge face is 41.4 ft. The bridge is supported by a vertical, concrete abutment with wingwalls on the left and by a vertical, stone abutment with stone wingwalls with a concrete cap on the right. The channel is skewed approximately 5 degrees to the opening while the computed opening-skew-to-roadway is 10 degrees. The only scour protection measure at the site was a stone wall along the upstream left bank and type-2 stone fill (less than 36 inches diameter) along the entire base length of the upstream left wingwall, left abutment, and downstream left wing wall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100-year and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was 0.0 ft. Abutment scour ranged from 6.4 to 7.9 ft at the left abutment and from 11.8 to 14.9 ft at the right abutment. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scouredstreambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particlesize distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont

Level II scour analysis for Bridge 53 (CHESTH01180053) on Town Highway 118, crossing the Williams River, Chester, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure CHESTH01180053 on Town Highway 118 crossing the Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 20.8-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly suburban while the right bank upstream is pasture. There is a house on the right bank downstream and VT 103 runs parallel to the river along the left bank. In the study area, the Williams River has an incised, straight channel with a slope of approximately 0.005 ft/ft, an average channel top width of 64 ft and an average bank height of 7 ft. The channel bed material ranges from sand to boulder with a median grain size (D 50 ) of 58.0 mm (0.190 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 17, 1996, indicated that the reach was stable. The Town Highway 118 crossing of the Williams River is a 43-ft-long, one-lane bridge consisting of one 40-foot steel-beam span (Vermont Agency of Transportation, written communication, April 6, 1995). The opening length of the structure parallel to the bridge face is 37.6 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 5 degrees to the opening while the computed opening-skew-to-roadway is 10 degrees. A scour hole 0.5 ft deeper than the mean thalweg depth was observed at both abutments during the Level I assessment. Scour protection measures at the site include: type-3 stone fill (less than 48 inches diameter) along the left bank upstream and downstream and type-2 stone fill (less than 36 inches diameter) along the entire base length of the upstream left wingwall, at the upstream end of the left abutment, and at the upstream end of the downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was 0.0 ft. Abutment scour ranged from 5.8 to 6.8 ft at the left abutment and 9.4 to 14.4 ft at the right abutment. The worst-case abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont

Level II scour analysis for Bridge 8 (WELLTH00020008) on Town Highway 2, crossing Wells Brook, Wells, Vermont

This report provides the results of a detailed Level II analysis of scour potential at structure WELLTH00020008 on Town Highway 2 crossing the Wells Brook, Wells, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Taconic section of the New England physiographic province in southwestern Vermont. The 14.4-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover on the right overbanks is predominantly suburban while the immediate banks are vegetated with trees and brush. The left bank upstream and downstream is predominantly pasture. In the study area, the Wells Brook has an incised, straight channel with a slope of approximately 0.005 ft/ft, an average channel top width of 51 ft and an average bank height of 7 ft. The channel bed material ranges from gravel to boulder with a median grain size (D 50 ) of 48.6 mm (0.159 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 19, 1995, indicated that the reach was stable. The Town Highway 2 crossing of the Wells Brook is a 35-ft-long, two-lane bridge consisting of one 32-foot concrete span (Vermont Agency of Transportation, written communication, March 22, 1995). The opening length of the structure parallel to the bridge face is 31.7 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-toroadway is 5 degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the left bank upstream, and type-5 (placed stone wall) at the upstream end of the upstream left wingwall, at the downstream end of the downstream left wingwall, and along the downstream left bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.8 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Abutment scour ranged from 5.6 to 10.0 ft at the left abutment and from 3.1 to 4.2 ft at the right abutment. The worst-case abutment scour occurred at the incipient roadway-overtopping discharge at the left abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Vermont